(ANCHORAGE, Alaska)—During today’s repairs, Alaska Department of Transportation & Public Facilities (DOT&PF) bridge repair crews noted further damage to the girder that was struck by the dump truck in the Jan. 3 crash. The damaged beam has the potential to fall and must be removed to protect the safety of the highway users below.
DOT&PF using is an emergency contract to bring a contractor on board. Removal of the girder will begin as soon as the crew and equipment can mobilize to the site.
[content id=”79272″]
Traffic on Tudor is currently shifted away from the damaged girder and remains open to two through-lanes. Tudor Road users are being cautioned to be alert to the new configuration and reduce speeds when traveling in the area.
Updates will be posted at: https://dot.alaska.gov/bridgestrikejan3/
More information will be shared as it becomes available.